Dear Marc, Dear Todd,
Being in Paris, it will be hard for me to give you an exact number for
the remaining bottles at Jefferson Lab. Todd, can you check how many
premix bottles we have please?
For 8 weeks, we need to have 28 bottles (~2 days/bottle). I think there
might be 4 bottles left. Which means we have to order 24 premix bottles
to be sure we are ready in case of any failure from the mixing system.
What is the status concerning the MFCs? Are the ones with condensed
isobutane in winter fixed?
No expected issue with mixing system when we come back end of july?
(because of summer heat)
Kind regards,
Maxime
PS: Let me know if the order is not validated in time to have the
bottles for August 23rd.
On 12/06/2018 23:28, Marc McMullen wrote:
> Hi Maxime,
>
> Please make sure that you are aware of the amount of Ar/C4H10 premix
> bottles you currently have by the gas shed. Although the run is a
> little bit in the future, ordering the gas now would probably a good
> idea. Delivery takes about 6 to 8 weeks. I am sure you have an account
> of your usage of premix to help estimate how much should be ordered.
>
> Thanks,
>