thanks for the info tyler.
getting the appropriate permits , drilling, and anchoring is hallb engineering staff's responsiblity.
From: "Tyler Lemon" <tlemon at jlab.org>
To: "dsg-rich" <dsg-rich at jlab.org>, "Walt Akers / JLAB" <akers at jlab.org>
Sent: Monday, November 7, 2016 11:27:50 AM
Subject: [Dsg-rich] EEL 124 questions for RICH assembly
Dear George and Marc,
For anchoring the RICH assembly structure, we would need to drill about 6 inches into the clean room floor.
For the drilling process, Walt mentioned this morning we do need a blind penetration permit and also a silica dust hazard analysis. Would there be any other hazard analysis or safety steps we would need for the drilling in the clean room?
Best regards,
Tyler
_______________________________________________
Dsg-rich mailing list
Dsg-rich at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-rich
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20161107/f2c9eadc/attachment-0002.html>
More information about the Dsg-rich
mailing list