[Dsg-rich] anchoring of RICH structure

Marco Mirazita Marco.Mirazita at lnf.infn.it
Mon Oct 24 11:16:05 EDT 2016


Hi Tyler,
when I was at JLab we briefly discussed about the anchoring of the RICH 
structure to the floor (see attached plot).
During our assembly test in Italy, the structure was fixed through 
screwed bars glued in the holes of the floor.
We would like to know if this technique can also be used in the clean 
room at jlab. In this case, should we prowide the bars and the glue or 
do you have available at jlab this material?
Thank you,
Marco