Thanks, Walt.
George and Marc,
Please see Walt's email below regarding RICH assembly and the exit walkway.
Best regards,
Tyler
From: "Walt Akers / JLAB" <akers at jlab.org>
To: "Tyler Lemon" <tlemon at jlab.org>, "dsg-rich" <dsg-rich at jlab.org>
Sent: Thursday, October 27, 2016 10:11:43 AM
Subject: Re: Egress path during RICH assembly in EEL 124
Tyler:
The potential safety issues in a dynamic installation are
endless - particularly as changes are being made. As I
am currently managing several dozen installation areas,
I tend to focus on the larger constraints and must leave it
to the working groups and area safety wardens to identify
and assess these issues.
That said, I would encourage the person who raised this
question to look at the diagrams themselves and assess if
they think there is a problem that needs to be addressed.
If there is, I will integrate the recommended changes into
future plans.
Walt
Tyler Lemon wrote:
> Dear Walt,
>
> In the DSG weekly meeting, we discussed the layout of the big clean
> room during RICH assembly. The point was bought up that since there is
> only one exit door (the door through the gowning area), there needs to
> be a 36 inch wide, unobstructed walkway to this door from any part of
> the clean room. Have the layout diagrams taken this into account for
> the RICH assembly area?
>
> Best regards,
> Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20161027/bcd17158/attachment-0002.html>
More information about the Dsg-rich
mailing list