good list marc
are there no ETA s for the other items?
add another column (design completion date) for the items that are being designed.
hopefully the procurement will go quickly (less than a week).
typical time for PRs is 2 weeks !
add a coulmn for date submitted for procurement.
also enumerate the list.
From: "Marc Mcmullen" <mcmullen at jlab.org>
To: "dsg-rich" <dsg-rich at jlab.org>
Sent: Wednesday, August 2, 2017 11:04:30 AM
Subject: [Dsg-rich] RICH Stiffening tool components.xlsx
Hi,
Attached is the list of Stiffening tool components which need to be
manufactured for the RICH.
Thanks,
--
Marc McMullen
Detector Support Group
757-269-7738
_______________________________________________
Dsg-rich mailing list
Dsg-rich at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-rich
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170802/d6c3ce46/attachment-0002.html>
More information about the Dsg-rich
mailing list