Hi Matt and Bob ,
Here are the P&I diagrams for the changes, which are in red. Please
review and sign off.
Hi Jenord,
If you are available, we will need a mechanical examination done once
the work is completed. We are scheduling the install work on Friday, and
should have everything done by 2pm, if not earlier. Matt is scheduled to
do the leak/pressure test immediately after. We would like to energize
by C.O.B. on Friday.
Thanks,
--
Marc McMullen
Detector Support Group
757-269-7738
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RICH-N2-Mods_120617B.pdf
Type: application/pdf
Size: 47114 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-rich/attachments/20171206/79cdb805/attachment-0002.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RICH-AirCooling-Mods_120617.pdf
Type: application/pdf
Size: 49783 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-rich/attachments/20171206/79cdb805/attachment-0003.pdf>
More information about the Dsg-rich
mailing list