Thanks for the heads up.
I submitted the ODH form online for approval.
Jen
----- Original Message -----
From: "Marc McMullen" <mcmullen at jlab.org>
To: "Jennifer Williams" <jennifer at jlab.org>, "dsg-rich" <dsg-rich at jlab.org>
Cc: jbrock at jlab.org, "Matthew Marchlik" <marchlik at jlab.org>
Sent: Tuesday, December 5, 2017 11:05:08 AM
Subject: RICH N2 Flow during holidays
Hi Jen,
We are planning to use 4 Nitrogen dewars in parallel (instead of 2) in
the EEL for the RICH during the holiday shutdown. The target group has
agreed to remove all their tanks during the shutdown so that we will be
the only gas source in the 125/highbay area. Attached is my ODH form,
the O2% if all four regulators fail and instantly boil off would be 19.01.
This will require your approval before we set it up. Please let me know
when it is approved.
Thanks,
--
Marc McMullen
Detector Support Group