[Dsg-rich] Timeline for RICH assembly tasks
Tyler Lemon
tlemon at jlab.org
Tue Feb 7 13:24:39 EST 2017
Hello,
Attached is a timeline graphic for the upcoming RICH assembly tasks. Time assigned for all tasks is an estimate with additional time added in case of delays or schedule changes.
Three tasks (delivery of Box 1 and Box 4, drilling anchoring holes, and performing the load test) are colored yellow. These tasks rely on help from Hall B Engineering and will delay other tasks if not performed on time.
Best regards,
Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-rich/attachments/20170207/cb2d0c62/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RICH timeline graphic.pdf
Type: application/pdf
Size: 50168 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-rich/attachments/20170207/cb2d0c62/attachment-0001.pdf>
More information about the Dsg-rich
mailing list