We are preparing for the RICH detector assembly, which should start 
around the third week of March. TOSP 64632 (Assembly of the RICH 
detector) has been returned pending a 125% load test of the hand winch. 
This test will only be done after the assembly structure is completed, 
the schedule has the assembly of the structure completing on  March 13. 
Other than the 125% load test, the SME for Cranes and Hoists also 
requires an inspection of the shoulder eye bolts before he will sign the 
TOSP.

George Jacobs has informed me that conducting the load test is an 
engineered lift, and it must be reviewed/conducted by Hall B 
engineering. The documentation of the components (the winch and the 
pulley) are attached to the TOSP.

https://mis.jlab.org/mis/apps/mis_forms/operational_safety_procedure_form.cfm?entry_id=64632

Please let myself or Tyler Lemon know if we can assist with the location 
of documentation provided by INFN.