[Dsg-rich] Jlab/INFN RICH Stiffening Tool

Ryan Bruce ryan at gandrmetals.com
Tue Jul 11 10:04:41 EDT 2017


Marc,
	The parts for the stiffening tube are spread out between the machine shop for the drilling and tapping and the fab shop for fabrication.  Right now, we are probably 20-25% complete and we have plans to be almost complete by Monday.  Monday is probably a good day for you to come by and see the product before we send it out for powder coating.  

Thank You,

Ryan L. Bruce
Project Manager

G&R Metals
a MFS, Inc. Company
810 Kiwanis Street
Hampton, VA 23661
Ph:   757.244.5693
Fax: 757.245.1132

Ryan at gandrmetals.com

-----Original Message-----
From: Marc McMullen [mailto:mcmullen at jlab.org] 
Sent: Monday, July 10, 2017 5:35 PM
To: Ryan Bruce; 'dsg-rich'
Subject: Jlab/INFN RICH Stiffening Tool

Hi Ryan,

I left you a message but wanted to follow up with an email. The INFN group from Italy would like a status update on the Stiffening Tool being fabricated at GandR. Additionally, would it be possible for them to come and see the progress?