> Aerogel
> 1.) When should we expect to receive 2-cm thick tiles?
>
28 squared tiles (more than what we need) are ready for shipment. They
have been on hold due to an administrative issue we solved only yesterday.
8 tiles are being cut to fit on the RICH sides. We expect them in August.
> 2.) Are all previously received 3-cm tiles for RICH at JLab? If not, how many are not at JLab?
>
5 tiles are in Ferrara. We are going to send to JLab soon, later
in the second half of August.
>
> Spherical Mirrors
> 3.) What is the timeline for the spherical mirrors to return to JLab?
>
This largely depends on the JLab rapidy in organizing the shipments.
Material is ready at ECI. CMA is ready to inspect and resurface 10
mirros within August. In principle we can arrange a first group (most
critical) to be coated and back to JLab at the beginning of September.
> 4.) Will we need to arrange the shipment of mirrors from CMA to ECI again?
>
Yes. The alternative is INFN organizes it. We just assumed JLab
would be easier as already did it.
>
> Planar Mirrors
> 5.) When should we expect the planar mirrors to arrive at JLab?
>
Lateral ones will be dispacthed in one week together with a frontal
prototype. The two frontals will follow in the first half of September.
> 6.) Are there any acceptance tests that will need to be performed on the planar mirrors?
>
If we find a way (as they are big) we can do a reflectivity test.
Planarity will be measured at the company (as their process was
validated by counter-measurements done at INFN).
>
> Electronics
> 7.) When will the electronics assembly begin?
>
Tomorrow.
> 8.) When do we expect the dark box cover designed for the electronic panel to arrive at JLab?
>
I do not have a date yet. Not needed before middle of August.
> 9.) Are we still planning on doing preliminary cosmic test with only a small number of PMTs? If so, when will assembly for this begin?
>
Yes. We wants to start assembling it this week. Major missing
item is SSP firmware at the moment. There will be many more,
but we will figure out while assembling.
Ciao, Marco.
>
>