[Dsg-rich] Atlas Copco technician arriving at JLab at noon on Friday, July 28
DeAnn Maddox
maddox at jlab.org
Wed Jul 26 14:59:44 EDT 2017
Good Afternoon--
To date he hasn't registered which is a DOE requirement before he may access the site--please reach out to him and express the importance of the registration form--I have attached the link below
https://misportal.jlab.org/mis/cis/jris_reg_form/subcontractor_reg.cfm
DeAnn Maddox| Facilities Access/Work Control Coordinator
Thomas Jefferson National Accelerator Facility
Newport News, VA
757-269-7135 | maddox at jlab.org | www.jlab.org
From: "Tyler Lemon" <tlemon at jlab.org>
To: "dsg-rich" <dsg-rich at jlab.org>, "Douglas Tilles" <tilles at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Ed Folts" <folts at jlab.org>, "DeAnn Maddox" <maddox at jlab.org>
Sent: Wednesday, July 26, 2017 2:54:27 PM
Subject: Atlas Copco technician arriving at JLab at noon on Friday, July 28
Hello,
Paul Stanko, an Atlas Copco technician, will be at JLab on Friday July 28, 2017 at noon.
Paul will be assisting with the first power-up of both compressors used for the RICH air cooling system.
One compressor is located in EEL 125 and the second is located on the top deck of the Forward Carriage.
I will be escorting him to both compressor locations on Friday.
Best regards,
Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170726/5ba41851/attachment-0002.html>
More information about the Dsg-rich
mailing list