[Dsg-rich] RICH compressors successfully powered

DeAnn Maddox maddox at jlab.org
Mon Jul 31 08:56:50 EDT 2017


Good Morning 

No problem--glad to hear everything was successful

DeAnn Maddox| Facilities Access/Work Control Coordinator 
Thomas Jefferson National Accelerator Facility 
Newport News, VA 
757-269-7135 | maddox at jlab.org | www.jlab.org

----- Original Message -----
From: "Douglas Tilles" <tilles at jlab.org>
To: "Tyler Lemon" <tlemon at jlab.org>
Cc: "dsg-rich" <dsg-rich at jlab.org>, "DeAnn Maddox" <maddox at jlab.org>, "Walt Akers" <akers at jlab.org>, "Joshua Johnson" <joshua.johnson at us.atlascopco.com>, "paul stanko" <paul.stanko at us.atlascopco.com>
Sent: Monday, July 31, 2017 6:15:11 AM
Subject: Re: [Dsg-rich] RICH compressors successfully powered

Insure you put a Tag  (Do Not Operate) on the Compressor as the power is still on at the disconnect.

----- Original Message -----
From: "Tyler Lemon" <tlemon at jlab.org>
To: "dsg-rich" <dsg-rich at jlab.org>, "maddox" <maddox at jlab.org>, "Walt Akers" <akers at jlab.org>, "Joshua Johnson" <joshua.johnson at us.atlascopco.com>, "paul stanko" <paul.stanko at us.atlascopco.com>
Sent: Friday, July 28, 2017 4:56:41 PM
Subject: [Dsg-rich] RICH compressors successfully powered

Hello, 

This afternoon we successfully powered on both RICH compressors in the EEL and Hall B. 

For the compressor in the EEL, we turned it on and set a maximum output pressure of 70 psi on the compressor. We then let the compressor run until it turned itself off when reaching an output pressure of 70 psi. After this, we stopped the compressor and vented the attached gas tank. We also got the MAC address for this compressor and Brian has contacted Sergey to get an IP address assigned to the compressor. The compressor's emergency stop button has been pressed, preventing the compressor output from being enabled. 

For the compressor in Hall B, we only turned it on and made sure that it is able to run correctly. We left this compressor powered on, but not running. 

Thank you to DeAnn for making sure all visitors were properly registered to be able to get on site. Thank you to Walt for quickly arranging the short-notice electrical work that needed to be done today. Also, thank you to Paul and Joshua, the Atlas Copco representatives, for helping us get the compressors running. 

Best regards, 
Tyler 