Hello Valery, 

This morning we received the RICH electronic boards. The boxes are in EEL 121 small cleanroom's gowning area. What would be the timeline for testing and installing the electronics?\ 

Also, when would the air cooling system be needed? A rough date is needed to give Dave Meekins, RICH gas system Design Authority, adequate time to approve the gas system since it is a pressure system. We cannot operate the air cooling system without DA approval. 

Please let us know. 

Best regards, 
Tyler 