[Dsg-rich] exit window status report

Tyler Lemon tlemon at jlab.org
Tue May 16 09:43:34 EDT 2017


Hello, 

We are still waiting on the arrival of the transfer screw set we procured yesterday afternoon. The set is expected to arrive no later than tomorrow, but it may arrive today. 

To avoid a work stoppage due to not having the transfer screw set, Kevin and Tom are measuring for and marking the location of the required holes in the aluminum. They will then test drill a hole using a drill press. 

If they are able to precisely locate and drill the hole, they will continue measuring and marking hole locations until the transfer screw set arrives. 

Best regards, 
Tyler 