Hi Maxime,
Yes, I agree with this plan.
Regards,
Bob
On 5/17/2017 12:20 PM, mdefurne wrote:
>
> Hello,
>
> So after discussing with all the team at Saclay, it will be more
> convenient to assemble MVT in room 125. If we follow Tyler's layout,
> we would then assemble the MVT in the corner where we will have our
> wooden boxes.
>
> For the gas system, we will run all the tests in the clean room.
> Consequently, for friday 26th, we will need a bottle of pure argon in
> the clean room and a few tables so that we can put the tiles on it and
> test leaks the very first day we will start unpacking.
>
> For cosmics data, we will take it in the clean room as soon as the MVT
> is assembled. Do you agree with this plan?
>
> Regards and good luck for the run,
>
> Maxime
>
> Le 17/05/2017 à 11:23, Tyler Lemon a écrit :
>> Hello,
>>
>> Attached are minutes from today's meeting held with Walt Akers, DSG,
>> and MVT collaborators to discuss how EEL 125 could be arranged to
>> accommodate upcoming RICH and MVT tasks.
>>
>> Best regards,
>> Tyler
>>
>>
>> _______________________________________________
>> Dsg-mvt mailing list
>> Dsg-mvt at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/dsg-mvt
>
--
Bob Miller
Hall B Lead Engineer
Jefferson Lab
757 269-7867
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20170517/f479f54d/attachment-0002.html>
More information about the Dsg-rich
mailing list