[Dsg-rich] load test of stiffening tool complete
Tyler Lemon
tlemon at jlab.org
Thu Oct 19 17:00:37 EDT 2017
Hello,
This afternoon, the RICH stiffening tool was load tested. Photos taken during the load test will be sent tomorrow.
Yesterday and this morning, Marc, Brian, Pablo, George, and Amrit completed the assembly of the stiffening tool on the transport trolley.
This afternoon the stiffening tool was taken to the Test Lab for the load test. During the load test, the stiffening tool was tested in the horizontal position and at ~65-degree vertical position. For each position, the stiffening tool was held in place with the test load for ten minutes.
After the load test, the stiffening tool and trolley were left in the Test Lab. Tomorrow morning, we will move it back to the EEL and disassemble the stiffening tool from the trolley.
Thank you to Mark Loewus for writing the lift plan for the load test and providing crane support and also to Bobby Thomas for assisting during the load test.
Best regards,
Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-rich/attachments/20171019/4c893854/attachment.html>
More information about the Dsg-rich
mailing list