[Dsg-rich] DC trolley and weights for RICH load test to EEL
Tyler Lemon
tlemon at jlab.org
Thu Oct 12 15:25:37 EDT 2017
Hello George and Doug,
INFN collaborators would like to clarify that the part we need brought to the EEL is the cart used to transport the Drift Chambers. Attached is a sketch of this cart where the original cart is in white and the RICH modifications in yellow.
Is this the R3 strongback you are referring to?
Please let us know.
Best regards,
Tyler
From: "George Jacobs" <jacobsg at jlab.org>
To: "Douglas Tilles" <tilles at jlab.org>, "Mirazita Marco" <Marco.Mirazita at lnf.infn.it>
Cc: "dsg-rich" <dsg-rich at jlab.org>, "Bob Miller" <rmiller at jlab.org>
Sent: Thursday, October 12, 2017 1:06:06 PM
Subject: Re: [Dsg-rich] DC trolley and weights for RICH load test to EEL
Hi Doug,
This will use a R3 strong back as the "trolley" for the RICH, not R2. This "trolley" will also be used for the 2nd RICH detector next year.
George
On 10/12/2017 12:59 PM, Douglas Tilles wrote:
Please have George point out the R2 DC strong back he wants over to the EEL to Mark so he can show Calvin on Wed. Also point out what ever you need over there. The weight blocks will come at the same time with the Dyno
----- Original Message -----
From: "Marco Mirazita" <Marco.Mirazita at lnf.infn.it> To: "Tyler Lemon" <tlemon at jlab.org> Cc: "Bob Miller" <rmiller at jlab.org> , "Doug Tilles" <tilles at jlab.org> , "dsg-rich" <dsg-rich at jlab.org> Sent: Thursday, October 12, 2017 9:37:11 AM
Subject: Re: [Dsg-rich] DC trolley and weights for RICH load test to EEL
Hello Bob and Doug,
it would be very important if the trolley could be moved in the EEL by
Friday morning so that Dario can prepare the trolley for the load test
before he leaves on Saturday.
Thank you,
Marco
Il 2017-10-11 21:08 Tyler Lemon ha scritto:
BQ_BEGIN
Hello Bob and Doug,
On Thursday October 19, 2017 we are planning to perform the load test
of RICH's stiffening tool here in the EEL building's high bay area.
Hall B Engineering has to provide the additional weights (~1400 lb)
necessary for the load test.
Hall B Engineering should ensure that both the DC trolley and weights
are in the EEL no later than Wednesday October 18 so that there will
be enough time to prepare for the load test the following day.
Best regards,
Tyler
_______________________________________________
Dsg-rich mailing list Dsg-rich at jlab.org https://mailman.jlab.org/mailman/listinfo/dsg-rich
_______________________________________________
Dsg-rich mailing list Dsg-rich at jlab.org https://mailman.jlab.org/mailman/listinfo/dsg-rich
BQ_END
--
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606
(office) 757-269-7115
(cell) 757-876-0480
(email) jacobsg at jlab.org (website) https://userweb.jlab.org/~jacobsg
_______________________________________________
Dsg-rich mailing list
Dsg-rich at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-rich
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20171012/1d03a7b0/attachment-0002.html>
More information about the Dsg-rich
mailing list