[Dsg-rich] RICH N2 system automatic backup

Tyler Lemon tlemon at jlab.org
Fri Dec 14 12:40:41 EST 2018


Hello George,


Can you send Bob Miller and Bill Crahen the drawing, pressure systems numbers and any other documentation you have on the RICH N2 automatic back up?


Bill will be the DA for it.



Best regards,

Tyler


________________________________
From: Bob Miller <rmiller at jlab.org>
Sent: Friday, December 14, 2018 9:25 AM
To: Tyler Lemon
Cc: Bill Crahen; Amrit Yegneswaran
Subject: Fwd: Re: [Dsg-rich] RICH N2 system automatic backup


Hi Tyler,


Please send the drawings, pressure systems number, and whatever documentation you have to Bill Crahen and myself.


Bill will be the DA on this project.


Regards,

Bob


-------- Forwarded Message --------
Subject:        Re: [Dsg-rich] RICH N2 system automatic backup
Date:   Wed, 12 Dec 2018 19:39:33 -0500
From:   Amrit Yegneswaran <yeg at jlab.org><mailto:yeg at jlab.org>
To:     Marco Contalbrigo <mcontalb at fe.infn.it><mailto:mcontalb at fe.infn.it>, Patrizia Rossi <rossi at jlab.org><mailto:rossi at jlab.org>, Bob Miller <rmiller at jlab.org><mailto:rmiller at jlab.org>
CC:     dsg-rich <dsg-rich at jlab.org><mailto:dsg-rich at jlab.org>



bob,

please assign a design authority for the analysis and approval of the system.

thanks

amrit


________________________________
From: Dsg-rich <dsg-rich-bounces at jlab.org><mailto:dsg-rich-bounces at jlab.org> on behalf of Marco Contalbrigo <mcontalb at fe.infn.it><mailto:mcontalb at fe.infn.it>
Sent: Wednesday, December 12, 2018 3:33 PM
To: Patrizia Rossi
Cc: dsg-rich
Subject: Re: [Dsg-rich] RICH N2 system automatic backup

Dear Tyler,
thank to DSG for this nice upgrade!
Marco.

On Wed, 12 Dec 2018, Patrizia Rossi wrote:

> Very appreciated Christmas gift!! Thank you Tyler and DSG people!!
> Patrizia
>
> Sent from my iPhone
>
> On Dec 12, 2018, at 3:13 PM, Tyler Lemon <tlemon at jlab.org><mailto:tlemon at jlab.org> wrote:
>
>       Hello,
>
>
>       DSG has developed a system to automatically switch RICH to a back up
>       bank of nitrogen in the event that Hall B's main nitrogen supply is
>       stopped.
>
>
>       The system is designed to use a pneumatic valve operated using the
>
>       pressure from the main N2 supply line that will open if that supply
>       pressure drops. The open pneumatic valve will then allow N2 to flow to
>       RICH from a bank of nitrogen bottles. Attached is a revised RICH
>       nitrogen system diagram showing the new automatic switch-over
>       components.
>
>
>       George has assembled the new components and DSG would like to test them
>       at the beginning of next year after the holidays. To be able to do any
>       sort of testing, the components and test procedure will need to undergo
>       a pressure systems analysis by a Design Authority (DA).
>
>
>       DSG will provide the necessary documentation to the DA once one is
>       requested and assigned.
>
>
>       Best regards,
>
>       Tyler
>
>       <RICH-N2-valve panel-REV2..pdf>
>
>       _______________________________________________
>       Dsg-rich mailing list
>       Dsg-rich at jlab.org<mailto:Dsg-rich at jlab.org>
>       https://mailman.jlab.org/mailman/listinfo/dsg-rich
Dsg-rich Info Page<https://mailman.jlab.org/mailman/listinfo/dsg-rich>
mailman.jlab.org
Mailing list for Hall B RICH. Members of mailing list are DSG, INFN collaborators, and other JLab staff associated with RICH. To see the collection of prior postings to the list, visit the Dsg-rich Archives.. Using Dsg-rich


>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20181214/e37d670f/attachment-0002.html>


More information about the Dsg-rich mailing list