[dsg-hallb_rich] Delivery date for spherical mirror springs is Dec. 2021
Brian Eng
beng at jlab.org
Thu Sep 30 10:39:34 EDT 2021
Maybe see what the lead times are like from this company?
https://www.asraymond.com/catalog/D23040<https://www.asraymond.com/catalog/D23040X>
https://www.asraymond.com/catalog/D22550
Although it seems like that's just who Grainger is actually getting them from, but it's worth a shot. They also have a list of distributors who might actually have some stock on hand, but the few I tried all said ships from manufacturer in 1 week.
________________________________
From: dsg-hallb_rich <dsg-hallb_rich-bounces at jlab.org> on behalf of Tyler Lemon <tlemon at jlab.org>
Sent: Thursday, September 30, 2021 9:40 AM
To: dsg-hallb_rich at jlab.org <dsg-hallb_rich at jlab.org>
Subject: [dsg-hallb_rich] Delivery date for spherical mirror springs is Dec. 2021
Hello,
This week, I submitted an additional PR for the springs for the RICH spherical mirror support through Grainger since it was taking so long to submit the PR through the dim.molle.com website.
I received notice to day that delivery date for the Grainger springs have been pushed back to December 31, 2021 at the earliest due to part availability.
Do we want to look for more alternatives to get the springs earlier?
Since we seem to be having trouble at JLab, maybe it'd be better if the springs are procured in Italy and sent to JLab?
-Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20210930/ad4932d3/attachment.html>
More information about the dsg-hallb_rich
mailing list