Hi Bob,
Last I talked with you, Hall B Engineering's plan was to set up the RICH gas system the first week of April (week of April 4).
The timeline for RICH assembly seems to have shifted to where at least the nitrogen purge system will be needed for sealing tests starting early in the week of March 28.
With this, can the set up of the N2 purge system in the EEL be rescheduled to be available around March 28?
-Tyler