Dear Chris,
this morning we need about 1 hour to complete the installation of our 
mirrors.
We should postpone the start of the last part of the survey to about 
9am.
Best regards,
Marco


Il 2022-05-24 21:37 Chris Gould ha scritto:
> Yes we can support this.
> -------------------------
> 
> From: Tyler Lemon <tlemon at jlab.org>
> Sent: Tuesday, May 24, 2022 3:36:26 PM
> To: Chris Gould <gould at jlab.org>
> Cc: Marco, Mirazita <marco.mirazita at lnf.infn.it>;
> dsg-hallb_rich at jlab.org <dsg-hallb_rich at jlab.org>
> Subject: Re: second RICH survey
> 
> Hi Chris,
> 
> I haven’t gotten any response to my previous email about whether the
> second survey of RICH can be done tomorrow morning.
> 
> Can the survey be done tomorrow morning?
> 
> -Tyler
> 
> -------------------------
> 
> From: Tyler Lemon
> Sent: Tuesday, May 24, 2022 10:04:54 AM
> To: Chris Gould <gould at jlab.org>
> Cc: Marco, Mirazita <marco.mirazita at lnf.infn.it>
> Subject: second RICH survey
> 
>  Hi Chris,
> 
>  Could we schedule the second survey of the RICH in the cleanroom for
> tomorrow morning?
> 
>  We should be finished with the last mirror installation by then.
> 
>  Thanks!
> 
>  -Tyler