[dsg-svt] SVT work schedule for KPP
Amrit Yegneswaran
yeg at jlab.org
Tue Dec 13 11:45:06 EST 2016
attached in line, dsg schedule.
DSG hopes all gas system components are made available by Jan 15, 2017.
george, marc, sahin, mindy, and brian are working full time on the Hall B gas system for the KPP.
SVT schedule contingent to gas system progress.
hence, no promises
From: "Yuri Gotra" <gotra at jlab.org>
To: "dsg-svt" <dsg-svt at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Doug Tilles" <tilles at jlab.org>
Cc: "Patrizia Rossi" <rossi at jlab.org>, "Stepan Stepanyan" <stepanya at jlab.org>
Sent: Tuesday, December 13, 2016 10:08:30 AM
Subject: [dsg-svt] SVT work schedule for KPP
Here are the action items and the due dates for the SVT system in
preparation for the KPP.
The work requests are separate for the Mechanical Group (MG) and DSG.
Please let me know if there are issues with this schedule.
- lacing the R4 cables, DSG, 12/22
Scheduled 1/3/17 - 1/13/17; depends on manpower required for the Hall B gas system.
- testing the spare chiller after repair, MG, 12/22
- preparing SVT for transportation to the hall (de-cabling, cable
labeling/grouping), DSG, 01/16 - 01/20
Possible; depends on manpower required for the Hall B gas system.
- moving the SVT service cart to EEL, MG, 01/17
- mounting the crates, patch panel, HV distribution boxes, UPS on the
service cart, DSG, 01/18 - 01/20
Possible; depends on manpower required for the Hall B gas system.
- installing the monitoring system (pc's, monitors, CRIO, etc) in the
Hall B counting room, DSG, 01/16 - 01/20
Possible; depends on manpower required for the Hall B gas system.
- moving the SVT service cart to the hall and mounting it on the rails,
MG, 01/23- 01/24
- disconnecting the chiller, moving the cooling system to the hall, MG,
01/23- 01/24
- moving the network switches to the hall, configuring network for hall
operations, DSG, 01/23 - 01/24
Possible; depends on manpower required for the Hall B gas system.
- mounting the SVT protection tube on the support tube, MG, 01/24
- preparing SVT for transportation, transporting SVT to the hall,
mounting the SVT to the service cart, MG, 01/25
- connecting the cooling system, MG, 01/25
- connecting/routing the SVT cables and services on the service cart,
DSG, 01/26 - 01/28
Possible; depends on manpower required for the Hall B gas system.
Thank you
_______________________________________________
dsg-svt mailing list
dsg-svt at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-svt
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20161213/a53a5ea5/attachment-0002.html>
More information about the dsg-svt
mailing list