[dsg-svt] Cabling SVT inner barrel
Amrit Yegneswaran
yeg at jlab.org
Tue Nov 1 15:46:33 EDT 2016
Brian will not be doing the cabling.
there are other more pressing matters he has to attend to
I'll request a combination of Mindy, Amanda and Marc to help with this matter.
From: "Yuri Gotra" <gotra at jlab.org>
To: "dsg-svt" <dsg-svt at jlab.org>
Cc: "Patrizia Rossi" <rossi at jlab.org>
Sent: Tuesday, November 1, 2016 3:34:43 PM
Subject: [dsg-svt] Cabling SVT inner barrel
Today we mounted the inner barrel on the support tube. Cooling system is
connected.
Sahin is out till next week. It would be great if Brian could help with
cabling. We need to test each region before the outer region is
connected, starting with R1. Cables should be routed nicely, hopefully
they won't be disconnected for a long time. The goal is to have SVT
fully integrated and tested by end of month to be ready for the ERR in
December.
Thank you.
_______________________________________________
dsg-svt mailing list
dsg-svt at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-svt
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20161101/f7fa5a13/attachment-0002.html>
More information about the dsg-svt
mailing list