[dsg-svt] SVT workflow 10/11-10/14

Brian Eng beng at jlab.org
Tue Oct 11 18:04:30 EDT 2016


Hi Yuri,

Since I was (and will be for most of this week) be busy with magnet work (we did successfully ramp the Torus to 100A today!) Mindy will work with Sahin on connecting the cables.

Since you did have an item only to my name for today I went ahead and completed it. The R2 ambient sensors have been connected and verified working. I cable tied them to existing module bundles.
--
Brian Eng
Detector Support Group
757-269-6018

> On Oct 11, 2016, at 3:31 PM, Yuri Gotra <gotra at jlab.org> wrote:
> 
> My suggestion for this new email list would be to post here:
> 
> 1. Planned SVT activity
> 
> 2. SVT work requests
> 
> 3. Availability of DSG personnel involved in SVT support
> 
> Hopefully this would help to avoid schedule collisions (i.e. today a 10-minute job of mounting the Faraday cage was postponed till tomorrow due to schedule conflict which cased a one day delay of R2 calibration and R3 integration).
> 
> This week the repair activity will continue with testing R1-R2 and R3 integration.
> 
> R2 cabling is complete (Sahin, Yuri, Brian)
> 
> Tentative schedule:
> 
> 10/11 connect R2 ambient sensors and test functionality (Brian)
> 
> 10/12 8 am mount Faraday cage (Sahin)
> 
> 10/12 strain relief cable bundles (Sahin)
> 
> Power up and test R1/R2 10/12 (Yuri, Brian)
> 
> 10/13-10/14 Mount and connect R3 (Sahin, Brian, Yuri)
> 
> 10/14 Power up and test R1-R3 (Yuri, Brian)
> 
> Depending on the completion of these activities, next week the inner barrel mounting on the support tube and cabling can be scheduled. If I will be done with kludging of the modules this week next week R4 module replacement (3 modules) can be scheduled.
> 
> The goal for this month is to complete reintegration of SVT (R1-R4) and start stability test in preparation for the CVT integration (end of November).
> 





More information about the dsg-svt mailing list