[dsg-svt] SVT workflow 10/11-10/14

Yuri Gotra gotra at jlab.org
Tue Oct 11 15:31:13 EDT 2016


My suggestion for this new email list would be to post here:

1. Planned SVT activity

2. SVT work requests

3. Availability of DSG personnel involved in SVT support

Hopefully this would help to avoid schedule collisions (i.e. today a 
10-minute job of mounting the Faraday cage was postponed till tomorrow 
due to schedule conflict which cased a one day delay of R2 calibration 
and R3 integration).

This week the repair activity will continue with testing R1-R2 and R3 
integration.

R2 cabling is complete (Sahin, Yuri, Brian)

Tentative schedule:

10/11 connect R2 ambient sensors and test functionality (Brian)

10/12 8 am mount Faraday cage (Sahin)

10/12 strain relief cable bundles (Sahin)

Power up and test R1/R2 10/12 (Yuri, Brian)

10/13-10/14 Mount and connect R3 (Sahin, Brian, Yuri)

10/14 Power up and test R1-R3 (Yuri, Brian)

Depending on the completion of these activities, next week the inner 
barrel mounting on the support tube and cabling can be scheduled. If I 
will be done with kludging of the modules this week next week R4 module 
replacement (3 modules) can be scheduled.

The goal for this month is to complete reintegration of SVT (R1-R4) and 
start stability test in preparation for the CVT integration (end of 
November).


-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-svt/attachments/20161011/c4d3e5a1/attachment.vcf>


More information about the dsg-svt mailing list