[dsg-svt] SVT Move to Hall B
Brian Eng
beng at jlab.org
Fri Jan 20 14:07:12 EST 2017
Yes, the cables are in the cart and it just needs the corner posts and panels installed.
We have the patch panel box on the upstream flange area, if this is a problem we can remove the blocks, but we were trying to keep as much of it connected as possible to speed up re-connection.
> On Jan 20, 2017, at 1:59 PM, Robert Miller <rmiller at jlab.org> wrote:
>
> Hi Brian,
>
> Is the SVT ready to move as well?
>
> Bob
>
> Sent from my iPhone
>
>> On Jan 20, 2017, at 1:23 PM, Brian Eng <beng at jlab.org> wrote:
>>
>> Hi Bob,
>>
>> We finished loading the electronics into the cart today. Mindy and Sahin started wiring the networking (and they'll keep working on it while it is in the EEL), but that doesn't need to be complete prior to the move.
>>
>> So the cart is ready to be moved whenever the schedule permits.
>>
>> The chiller and its associated panel are still in EEL/124 since we weren't sure what the proper procedure is to move it.
>>
>> Let us know if you need any extra manpower when it comes time to move the stuff out of the EEL.
>> --
>> Brian Eng
>> Detector Support Group
>> 757-269-6018
>>
>>> On Jan 16, 2017, at 12:52 PM, Robert Miller <rmiller at jlab.org> wrote:
>>>
>>> Hi Brian,
>>>
>>> We can deliver it on Wednesday. Please contact the target group about leaving the cart in their area while you are loading it with your electronics.
>>>
>>> Bob
>>>
>>> Sent from my iPhone
>>>
>>>> On Jan 13, 2017, at 2:48 PM, Brian Eng <beng at jlab.org> wrote:
>>>>
>>>> Hi Bob,
>>>>
>>>> Could you give us a heads up a day or so before the cart is moved to the EEL from physics storage so we can power down, begin to de-cable the SVT, and remove the crates from the racks?
>>>>
>>>> Since I think the longest amount of time will be spent reconnecting everything when it's moved to the Hall the less time it spends in the EEL the better.
>>>>
>>>> Thanks
>>>>
>>>> P.S. Just to keep everyone in the loop Bob expects the cart will arrive in the EEL sometime next week, but probably won't go to the Hall until the week of the 23rd.
>>
More information about the dsg-svt
mailing list