Thank you Brian,

Please let me know when you are ready and we will schedule the work. For 
the next weeks we will be mostly taking long cosmic runs for alignment. 
Gas leaks are small, the premixed bottles we have should last. Saclay 
team will arrive beginning of October. Irakli is asking for a VXS crate, 
I am planning to give him temporary the one from R4. They will set up a 
test bench in EEL125 for a month to work on MVT/FTT/BONUS.

On 9/8/17 1:21 PM, Brian Eng wrote:
> Hi Yuri,
>
> In regards to the first point: Mindy has completed machining and assembly of the new patch panel box and I guess we'll install it sometime next week when the SVT is powered off. The initial plan is to just transfer the existing terminal blocks over without disconnecting all the cables, if that works out it hopefully will only take a few hours to complete.
>
> I'm not sure on the other one.

-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20170908/78a65c0c/attachment-0002.vcf>


More information about the dsg-svt mailing list