Dear All,

Here is the sequence of tasks for the CVT integration and commissioning 
in EEL124 and in the hall  during the SAD (resources needed are listed 
in parentheses):

- modify the SVT hardware interlock system (DSG)

- modify the CVT thermal insulation (hall)

- order the MVT premix gas bottles (hall)

- renew the CVT integration and commissioning OSPs

- move the BMT support, crates and services to EEL124 (hall)

- install the MVT gas services in EEL124 (hall and DSG)

- install the SVT dry air high flow purging system in EEL124 (hall)

- install the CVT racks and crates in EEL124 (DSG)

- move the CVT integration cart to EEL124 (hall)

- install the SVT cooling system in EEL124 (hall)

- install anti-static mats and cable trays in EEL124 (DSG)

- mount the SVT on the support tube (hall)

- align and survey the SVT (survey)

- connect the SVT services (DSG)

- commission the SVT DAQ and services

- install the SVT standalone trigger (FE)

- commission the SVT on cosmics, standalone trigger

- integrate the BMT detector

- install the BMT DAQ in EEL124

- mount the BMT on the integration cart (hall)

- align and survey the BMT (survey)

- connect the BMT services (DSG)

- commission the BMT DAQ and services

- commission the CVT on cosmics, the SVT cosmic trigger

- transport the CVT to the hall

- transport and install the CVT electronics and services in the hall 
(hall, DSG)

- install the CVT on the space frame cart (hall)

- align and survey the CVT (survey)

- connect and commission the CVT services (DSG)

- commission the CVT DAQ

- commission the CVT on cosmics, CTOF trigger


On 8/14/20 3:14 PM, Stepan Stepanyan wrote:
> Dear all,
>
> In preparation for a long shutdown (SAD) from September 21, 2020, to June 2021, we are compiling a list of activities in Hall-B, with priorities and resources needed. If you have planned work during this time, please send a prioritized list of tasks with necessary resources to Bob, Denny and me by next Friday, August 21.
>
> Regards, Stepan
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20200819/48d8dbc8/attachment.vcf>


More information about the dsg-hallb_svt mailing list