Here is the (preliminary) sequence of tasks for the DAQ/Trigger:

  *   CAEN TDC and VXS backplanes replacement with new boards
  *   DC trigger development
  *   work on streaming test setups
  *   dcrb modification and drift chamber testing
  *   Old HV controllers separation from daq crates (in conjunction with new DC HV installation)
  *   Moller FADC daq setup
  *   helicity correction board/signals setup
  *   CODA software work (CentOS7 for VME and VTP controllers, high performance testing, bug fixing etc)
  *   ADCs for the raster system
  *   consider need computer for counting room bluejeans and improve remote work procedures