Hi Mike,
There are several advantages to having the PLC licenses on the Jlab
license server infrastructure.
For the licenses located on the Jlab license server infrastructure, the
computer center is responsible for support and maintenance therefore, I
think we should use the existing Jlab license server infrastructure.
Halls B and D use the Jlab license server infrastructure for their PLC
licenses. By locating the Hall C licenses on the Jlab license server
infrastructure, we will move towards a unified system for the physics
division. And by having a unified system it will facilitate DSG support
for Halls B, C, and D.
With regards to the Hall C PLC licenses, we will limit access on the
Jlab license server infrastructure to /*only /*approved*/ by Hall C
*/**users (as mentioned by Pablo), so there should be no issue regarding
unauthorized users.
Finally, placing the licenses on the Jlab license server infrastructure
will enable other DSG members, Amrit and Mary Ann, who do not have a
computer with access to the Hall C subnet, to participate in the project.
Unless there are compelling reasons to locate the licenses on Skylla7,
my recommendation is that we locate the licenses on Jlab license server
infrastructure.
Regards,
Peter
On 6/8/2018 8:52 AM, Mike Fowler wrote:
> PLC task report snippet
>
>>>> Acquired two RS-Logix5000 licenses Full edition
> >>> Generated CCPR to run licenses on Computer Center server.
> >>> Server computer will be supported by computer center
> >>> Requested limited access for users to use the licenses.
>
> Hello,
>
> The Logix5000 licenses purchased with Hall C funds should be installed on the Hall C computer Skylla7 where access is limited to Hall C Rockwell software users and managed by Hall C staff.
>
> Regards,
> Mike
>
>
>
>
>
> ----- Original Message -----
> From: "Pablo Campero" <campero at jlab.org>
> To: "dsg-hallc controls" <dsg-hallc_controls at jlab.org>
> Cc: "rossi patrizia" <rossi at jlab.org>
> Sent: Friday, June 1, 2018 3:38:16 PM
> Subject: [Dsg-hallc_controls] PLC tasks report
>
> Hello,
>
> Please attached find PLC task report that shows the current status of the tasks assigned to DSG.
>
>
> Best Regards,
> Pablo
>
> _______________________________________________
> Dsg-hallc_controls mailing list
> Dsg-hallc_controls at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallc_controls
>
> _______________________________________________
> Dsg-hallc_controls mailing list
> Dsg-hallc_controls at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallc_controls
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallc_controls/attachments/20180608/20b25ab4/attachment-0001.html>
More information about the Dsg-hallc_controls
mailing list