[Dsg-hallc_controls] PLC tasks report
Mike Fowler
fowler at jlab.org
Fri Jun 8 12:11:56 EDT 2018
Hello Peter,
Regarding you note:
>>the computer center is responsible for support and maintenance
Very little support and maintenance is required for two computer files.
>> by having a unified system it will facilitate DSG support for Halls B, C, and D.
It is our understanding that the DSG has/used Rockwell software licenses to support Hall B & D.
If the new license are solely for Hall C support, we see no reason for the use of a non Hall C server.
>> we will limit access on the Jlab license server infrastructure to /*only /*approved*/ by Hall C
Who in DSG will limit access?
>>Finally, placing the licenses on the Jlab license server infrastructure will enable other DSG members, Amrit and Mary Ann, who do not have a computer with access to the Hall C subnet, to participate in the project.
"DSG task report snippet"
>Configured five computers on Hall C Development subnet.
> Computers rebuilt with Windows 7.
> Installed RSLogix 5000 (v. 16.04) using “skylla7” as license server.
According to the DSG task report, DSG has five computers on the Hall C subnet with access to the license server on Skylla7.
Hall C has two RSLogix license, DSG has two, that covers four of the five DSG computers. The license can also be used on a temporary basics, multiple times, for a seven day period.
>>Unless there are compelling reasons to locate the licenses on Skylla7, Regards, Peter
We seen no compelling reason to use a central server.
Regards,
Mike
On 6/8/2018 8:52 AM, Mike Fowler wrote:
> PLC task report snippet
>
>>>> Acquired two RS-Logix5000 licenses Full edition
> >>> Generated CCPR to run licenses on Computer Center server.
> >>> Server computer will be supported by computer center
> >>> Requested limited access for users to use the licenses.
>
> Hello,
>
> The Logix5000 licenses purchased with Hall C funds should be installed on the Hall C computer Skylla7 where access is limited to Hall C Rockwell software users and managed by Hall C staff.
>
> Regards,
> Mike
>
>
>
>
>
> ----- Original Message -----
> From: "Pablo Campero" <campero at jlab.org>
> To: "dsg-hallc controls" <dsg-hallc_controls at jlab.org>
> Cc: "rossi patrizia" <rossi at jlab.org>
> Sent: Friday, June 1, 2018 3:38:16 PM
> Subject: [Dsg-hallc_controls] PLC tasks report
>
> Hello,
>
> Please attached find PLC task report that shows the current status of the tasks assigned to DSG.
>
>
> Best Regards,
> Pablo
>
> _______________________________________________
> Dsg-hallc_controls mailing list
> Dsg-hallc_controls at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallc_controls
>
> _______________________________________________
> Dsg-hallc_controls mailing list
> Dsg-hallc_controls at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallc_controls
More information about the Dsg-hallc_controls
mailing list