[Dsg-hallc_controls] Hall C NPS cable work for DSG

Brad Sawatzky brads at jlab.org
Tue Oct 29 16:53:18 EDT 2019


If we are still going with the Radiall connector (last information I
had), then I also have set of HV crimp tools and a few connectors that
arrived from the Glasgow group last week.

-- Brad

On Tue, 29 Oct 2019, Jack Segal wrote:

> Thanks for the reminder. I have not heard of anything new. I was reminded to order the RG174/U cable. Just did. 2000 ft. in stock.
> Should be in soon. I have the Molex connector and crimp tools on hand. I have the SMA connector on hand. The HV connector is past
> due and I asked Jami to check on it. The example cable is on my desk in the EEL. I can bring it down and we can talk about how you
> folks want to proceed at this point. I have not tried to assemble one of these.
> 
> On 10/29/2019 12:47 PM, Peter Bonneau wrote:
> > Hi Jack,
> > 
> > We understand there is a delay for the NPS work in Hall C.
> > If you could keep us in the loop regarding the new due date for this project, we'll be able to schedule the NPS cabling work in with our other DSG projects.
> > 
> > Regards,
> > Peter
> > 
> 
-- 
Brad Sawatzky, PhD <brads at jlab.org>  -<>-  Jefferson Lab / Hall C / C111
Ph: 757-269-5947  -<>-  Fax: 757-269-5235  -<>- Pager: brads-page at jlab.org
The most exciting phrase to hear in science, the one that heralds new
  discoveries, is not "Eureka!" but "That's funny..."   -- Isaac Asimov


More information about the Dsg-hallc_controls mailing list