Hi Mark and Bogdan,
Just wanted to get some clarification with what's going on with the divider bases alteration/installation.
It was my understanding that there were already 150 bases with the capacitors added and Mindy has completed ~150 as of today.
Have they all been installed within the past day by the French team?
Is this the pace that can be expected for the remainder?
If this is the case, we definitely would not be able to keep up with that pace due to our current work load and someone from another team would need to be pulled in to help.
Thanks,
Aaron