Hi Bryan et al,
Just wanted to follow up with regards to the LED controls programming.
We have finished the layout of the control GUI.
Brian and I have gone over the information in the Github.
Is there any additional documentation detailing exactly what the PVs control.
What is not obvious is if the pulse frequency is hard coded in the PV and exactly what channels are controlled by a PV.
Is there a newer version beyond this beta version?
-- Aaron
________________________________
From: Bryan Moffit <moffit at jlab.org>
Sent: Monday, December 5, 2022 7:57 AM
To: Aaron Brown <ambrown at jlab.org>; Brad Sawatzky <brads at jlab.org>; dsg-hallc_nps at jlab.org <dsg-hallc_nps at jlab.org>
Cc: Brian Eng <beng at jlab.org>; William Gu <jgu at jlab.org>; Chris Cuevas <cuevas at jlab.org>; Robert Michaels <rom at jlab.org>
Subject: Re: [EXTERNAL] NPS LED/VLD controller specs/information/summary
I've pushed a 'beta' version of the vld-epics driver to github:
https://github.com/JeffersonLab/vld-epics
It has read/write support to the VLD parameters, but does not yet
include 'automated' specific procedure support (bleaching, calibration
pulse).
I'm starting to code up that procedure support into the vld library
(which has also been updated). We ought to talk about specifics for the
bleaching / calibration pulse functionality and driver hooks to your UI.
On 22-Nov-22 5:36 PM, Aaron Brown wrote:
> Hi Brad,
>
> Brian will be on vacation from 11/24/2022 until 01/03/2023.
> He will begin working on the control scripts that utilize the existing
> Linux drivers and is confident that this can be completed by early
> January 2023.
> With regards to the "Beta quality GUI", the EPICS drivers would need to
> be completed before we could finish this.
> The layout of the GUI is done, we just need the PVs before we can move
> to the testing/debugging phase.
> for the EPICS drivers, it would be a good idea to see if someone from
> the FE/DAQ group could complete the task.
>
> Happy Thanksgiving!
>
> -- Aaron
> ------------------------------------------------------------------------
> *From:* Brad Sawatzky <brads at jlab.org>
> *Sent:* Monday, November 21, 2022 6:42 PM
> *To:* Bryan Moffit <moffit at jlab.org>; dsg-hallc_nps at jlab.org
> <dsg-hallc_nps at jlab.org>
> *Cc:* Brian Eng <beng at jlab.org>; Aaron Brown <ambrown at jlab.org>; William
> Gu <jgu at jlab.org>; Chris Cuevas <cuevas at jlab.org>; Robert Michaels
> <rom at jlab.org>
> *Subject:* [EXTERNAL] NPS LED/VLD controller specs/information/summary
> After recent discussions with Bryan and William, I volunteered to send
> out a status/summary on the NPS LED/VLD needs for the near (Dec/Jan)
> and medium term (Feb/Mar).
>
>
> - Operational specs for the LED pulser are in William's directories.
> - His software libraries and test code can be found here:
> /group/da/distribution/coda/Hardwaremanual/VLD/
> or from the CODA web page. The test software can be accessed from
> /daqfs/home/jgu/Triggersoftware/trigger.c, VLDtestN functions.
> There are docx files in the /group directory with specs and technical
> details. Ideally we would be running the software under linux (intel
> vme computer), so any vxworks specific code should be updated to
> compile in that environment.
> - I am attaching what I think is the most recent spec document for
> easy access: 'VLD.docx'
>
> - A Control/GUI requirements summary is attached as a text file.
> - See: 'LED-GUI-summary-21Nov2022.txt'
>
> - Here is a link to some (intel controller) development code from Bryan
> Moffit:
> https://urldefense.proofpoint.com/v2/url?u=https-3A__github.com_JeffersonLab_vld&d=DwIDAw&c=CJqEzB1piLOyyvZjb8YUQw&r=TkJUDpm1-rWCci4nhe47n5XMOLWvRg1TNSqSgPyxyhs&m=1N3fMPIfm78FoxmXp_mXreXU8E0U2i30VAPa6A-PqDvhIBy5Wm1U9gzMBHv6iWyH&s=B6Fs97LKHZhH97IC2bajCCDXfhExhHaLYIvGerKATkM&e= <https://urldefense.proofpoint.com/v2/url?u=https-3A__github.com_JeffersonLab_vld&d=DwIDAw&c=CJqEzB1piLOyyvZjb8YUQw&r=TkJUDpm1-rWCci4nhe47n5XMOLWvRg1TNSqSgPyxyhs&m=1N3fMPIfm78FoxmXp_mXreXU8E0U2i30VAPa6A-PqDvhIBy5Wm1U9gzMBHv6iWyH&s=B6Fs97LKHZhH97IC2bajCCDXfhExhHaLYIvGerKATkM&e=>
>
>
> ---------------------------------------------
> Near Term Requirements (ie. late-Dec/early-January)
> ---------------------------------------------
> - We don't need a full working GUI, but we do need a clear, student-
> accessible way to run specific tests.
> * I am imagining a set of pre-compiled, special-case binaries or
> script(s) that are run from a command-line running on the VME
> contoller(s)
>
> - The scripts should be able to do the following:
> A. Turn all LED on in bleach mode
> * This should also set the Trg_out NIM ouput logic HI *first*
> and that needs to be tied into the HV interlock circuit.
>
> B. Pulse one or more specified LEDs when a pulse is seen on the VLD
> Trg/Clk input.
> - The list of LEDs to be activated, pulse characteristics, etc can
> either be hardcoded, or read-in via a config file. Doesn't have
> to be perfect, just needs to work. We can fine-tune later.
>
>
> ---------------------------------------------
> 'Beta' quality GUI (Feb, early-March)
> ---------------------------------------------
> - NPS installation begins this spring -- that will come very soon!
>
> * We will need at least a 'beta' quality (ie. feature complete, but may
> be buggy) GUI by Feb/early-March so we can test and fix bugs before
> the systems is disassembled and moved to the Hall. It will be a while
> before it is working again in the Hall and we definitely do not want
> to leave testing this critical system to the summer.
>
> -- Brad
>
> --
> Brad Sawatzky (he/him), PhD <brads at jlab.org> -<>- Jefferson Lab/SciComp/F272
> Ph: 757-269-5947 -<>- Fax: 757-269-5235 -<>- Pager: brads-page at jlab.org
> The most exciting phrase to hear in science, the one that heralds new
> discoveries, is not "Eureka!" but "That's funny..." -- Isaac Asimov
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallc_nps/attachments/20230119/da603c78/attachment.html>
More information about the Dsg-hallc_nps
mailing list