[Dsg-hallc_nps] DSG-NPS Status update
Aaron Brown
ambrown at jlab.org
Tue Jan 24 23:42:12 EST 2023
Hi Everyone,
Attached please find an Excel document detailing the status of the various task to be completed by DSG prior to detector testing in EEL 108.
A couple of lines I'd like to bring attention to:
Line 19: Currently it is takes roughly 2 days to complete 1 extension cable. This puts the estimated date of completion around 2023/02/07.
Line 21: The VLD control GUI has been laid out. We're just waiting to receive documentation regarding the PVs from Bryan Moffit who returns to the lab at the beginning of February
Have a good evening!
Thanks,
Aaron
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallc_nps/attachments/20230125/4a95f823/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: eel testing.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 9887 bytes
Desc: eel testing.xlsx
URL: <https://mailman.jlab.org/pipermail/dsg-hallc_nps/attachments/20230125/4a95f823/attachment.xlsx>
More information about the Dsg-hallc_nps
mailing list