[dsg-hdice] Pump cart lock-out
Amanda Hoebel
amandah at jlab.org
Fri Dec 2 15:09:06 EST 2016
Hi Xiangdong,
That sounds good. I will meet with you Monday.
Thanks,
Amanda
----- Original Message -----
From: "Xiangdong Wei" <xwei at jlab.org>
To: "Amanda Hoebel" <amandah at jlab.org>
Sent: Friday, December 2, 2016 1:40:25 PM
Subject: Re: [dsg-hdice] Pump cart lock-out
Hi Amanda,
Mike Lowry was sick on Wednesday and has not shown up since then. I'm quite busy this afternoon and could barely spend any time in HDice lab. Mike should be back on Monday. But if he were still out then, I can check the pump cart power status with you after Ball-B staff meeting (10:30am) on Monday. How is it sound?
Thanks,
Xiangdong
Xiangdong Wei
x-5266
From: "Amanda Hoebel" <amandah at jlab.org>
To: dsg-hdice at jlab.org
Cc: "Patrizia Rossi" <rossi at jlab.org>
Sent: Friday, December 2, 2016 10:08:29 AM
Subject: [dsg-hdice] Pump cart lock-out
Hi,
Mindy, Sahin, and I will be working to generate the wiring diagram for the HDice pump cart. In order to safely work on the pump cart all sources of energy need to be identified and locked out. We have all obtained LTT training and will be purchasing locks on the BOPS account. After turning off and locking out energy sources, someone from the HDice group who is familiar with the energization of the pump cart will need to inspect the lock boxes to ensure all sources of energy are turned off and locked out. I will be present for the lock-out inspection.
Regards,
Amanda
_______________________________________________
dsg-hdice mailing list
dsg-hdice at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-hdice
More information about the dsg-hdice
mailing list