Hi Tyler,

I will ask Ed if we can start Monday.  He mentioned in his last email 
that to start the trial "This will require a computer connected to the
instrument that I can gain remote control over through teamviewer to
activate the option."

I won't have access to a PC connected to the Lock-In amplifier until
Tuesday.  Tyler, would you have access to a PC Monday?  If so, would you
have time on Monday to have a virtual meeting with Ed so he can activate
the trial?

Thanks,
Tom

> Hi Tom,
>
> It seems like the best option would be to see if the trial period could
> start on Monday. That way there'd be enough time for you all in HDice to
> look into it, too.
>
> I do not think it would be possible to write a program for the boxcar
> averager during the one week trial period. Using the boxcar averager
> during the trial period would have to be done through "manual" set up like
> what was shown in the demo.
>
> To not waste any part of the trial period, it might be a good idea to also
> talk to Ed and verify the best way to set up the signals for the boxcar
> averager. If I remember correctly from the demo, the signal detected from
> the lock-in amplifier would need to be output through one of the Zurich
> lock-in amplifier's auxiliary outputs and then into the boxcar averager
> input.
>
> Tyler
> ________________________________
> From: thomaso at jlab.org <thomaso at jlab.org>
> Sent: Friday, October 9, 2020 2:28 PM
> To: Tyler Lemon <tlemon at jlab.org>
> Subject: Re: [dsg-hdice] Boxcar Averager Trial Dates
>
> Hi Tyler,
>
> I was speaking to Xiangdong today about our schedules.  We will be
> starting Run 2 of the experiment by the 26th.  He believes him and I will
> be too busy with running the experiment at UITF to be able to work on the
> Boxcar Averager at this point.
>
> He came up with two suggestions.  First would be to activate the trial
> possibly today (or more realistically Monday) if you have time to start
> checking out the Boxcar features before your vacation.
>
> The second option would be to start the trial on 10/26 when you are back.
> Xiangdong pointed out that if we wait until then, it wouldn't give us much
> time before we'd need the device for taking actual measurements. Also,
> Xiangdong said we would have to let the DSG take over working with the
> Boxcar Averager since all our time will be devoted to Run 2 of the
> experiment. He wasn't sure how long you would need to investigate the
> device/LabOne, write a program, and test before needing to take actual
> measurements.
>
>
> Let me know what you think about the situation when you have a chance.
>
>
> Thanks,
> Tom
>
>
>> Hi Tom,
>>
>> I will be on vacation from 10/17 through 10/25, so would it be possible
>> to
>> have trial period starting 10/26?
>>
>> Tyler
>> ________________________________
>> From: dsg-hdice <dsg-hdice-bounces at jlab.org> on behalf of
>> thomaso at jlab.org
>> <thomaso at jlab.org>
>> Sent: Friday, October 9, 2020 12:15 AM
>> To: dsg-hdice at jlab.org <dsg-hdice at jlab.org>
>> Subject: [dsg-hdice] Boxcar Averager Trial Dates
>>
>> Hi Tyler,
>>
>> I'm working with Ed, from Zurich, to schedule the 1 week trial for the
>> Boxcar Averager.  I was thinking of asking the trial to be from
>> Wednesday
>> October 14th to Wednesday October 21st given the HDice schedule.
>>
>> However I wanted to check with you and your group first to see if that
>> time frame works with your schedules should you want to try out the new
>> features?
>>
>> Thanks,
>> Tom
>>
>> _______________________________________________
>> dsg-hdice mailing list
>> dsg-hdice at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/dsg-hdice
>>
>
>
>




More information about the dsg-hdice mailing list