[dsg-hdice] Zurich lock-in amplifier availability affects fsNMR development

thomaso at jlab.org thomaso at jlab.org
Wed Sep 16 15:21:51 EDT 2020


Hi Tyler,

My mistake.  I forgot to close LabOne tab in the browser.  I'll run back
over and take care of that.  I'll email you back when it's done.  Sorry
about that.

-Tom

> Hi Xiangdong and Tom,
>
> LabOne still says that the lock-in amplifier is in use by 129.57.86.128
> (HDiceNMR4's IP). See attached screenshot.
>
> LabVIEW won't connect to it unless the device is available and not in use.
>
> Tyler
> ________________________________
> From: thomaso at jlab.org <thomaso at jlab.org>
> Sent: Wednesday, September 16, 2020 3:17 PM
> To: Xiangdong Wei <xwei at jlab.org>
> Cc: Tyler Lemon <tlemon at jlab.org>; dsg-hdice at jlab.org <dsg-hdice at jlab.org>
> Subject: Re: [dsg-hdice] Zurich lock-in amplifier availability affects
> fsNMR development
>
> Hi Tyler,
>
> I'm not running anything at the moment. The Lock-In is available for you
> to use.  Do you need access to the PC too?  If you do, I'll log off.  If
> not, the Lock-In Amplifier is free to use.
>
> -Tom
>
>> Tyler,
>>
>> I don't think we are using it today.  moved Rack 2 with HDiceNMR2 to the
>> UITF last night---I start setting up for the IBC there. Let me check
>> with
>> Tom to see if he is running it or not.
>>
>> Thanks,
>>
>> Xiangdong
>> ________________________________
>> From: dsg-hdice <dsg-hdice-bounces at jlab.org> on behalf of Tyler Lemon
>> <tlemon at jlab.org>
>> Sent: Wednesday, September 16, 2020 2:52 PM
>> To: dsg-hdice at jlab.org <dsg-hdice at jlab.org>
>> Subject: [dsg-hdice] Zurich lock-in amplifier availability affects fsNMR
>> development
>>
>> Hello Xiangdong,
>>
>> We are to the point where we could start programming drivers in LabVIEW
>> for the Zurich lock-in amplifier. To be able to do so, I will need the
>> lock-in amplifier to be available.
>>
>> Since it is on the network, I can see with the LabOne program that the
>> Zurich lock-in amplifier has been in almost continuous use by HDice
>> group
>> 's PC HDiceNMR4.
>>
>> If DSG is unable to have regular and extended access to the lock-in
>> amplifier, it will delay the completion of the new
>> Zurich-lock-in-amplifier-based fsNMR program.
>>
>> We could talk about this further in tomorrow's DSG-HDice meeting.
>>
>> -Tyler
>> _______________________________________________
>> dsg-hdice mailing list
>> dsg-hdice at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/dsg-hdice
>>
>
>
>




More information about the dsg-hdice mailing list