[E12-15-001] Fwd: [Hallc] [New Logentry] Hall C RC update: Thursday, July 4

Alexandre Camsonne camsonne at jlab.org
Thu Jul 4 16:57:34 EDT 2019


---------- Forwarded message ---------
From: <gaskelld at jlab.org>
Date: Thu, Jul 4, 2019, 13:50
Subject: [Hallc] [New Logentry] Hall C RC update: Thursday, July 4
To: <hallc_running at jlab.org>, <hallc at jlab.org>


Hall C RC update: Thursday, July 4 <https://logbooks.jlab.org/entry/3698663>

   - Edit
   <https://logbooks.jlab.org/entry/3698663/edit?destination=email/send>
   - Delete
   <https://logbooks.jlab.org/entry/3698663/delete?destination=email/send>

Lognumber 3698663 <https://logbooks.jlab.org/entry/3698663>. Submitted by
gaskelld <https://logbooks.jlab.org/user/gaskelld> on Thu, 07/04/2019 -
13:45
<https://logbooks.jlab.org/entries?start_date=1562258740&end_date=1562265940&book=HCLOG>.

Logbooks: HCLOG <https://logbooks.jlab.org/book/hclog>

Accelerator recovery proceeds, but estimated time of beam for physics has
shifted a little. The North Linac cryomodules should be full by ~ end of
day shift today, and the South Linac tomorrow. Beam recovery starts
immediately after. On the White Board schedule, "restore" should last
through Sunday OWL, with tune beam in the halls during day shift Sunday.

Despite the shift in expected beam start, we will still plan on condensing
the target Friday in order to be ready for beam on Sunday.

Aside from target operators, shifts for Friday and Saturday OWL and DAY are
cancelled. Saturday SWING and Sunday OWL are on Standby. Target operators
should start reporting Friday, DAY shift.

There will be no RC meeting today. We will meet tomorrow at the usual time.
_______________________________________________
Hallc mailing list
Hallc at jlab.org
https://mailman.jlab.org/mailman/listinfo/hallc
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/e12-15-001/attachments/20190704/50a51efc/attachment.html>