[Eicatjlab_all_personnel] [EXTERNAL] Review Planning for CD-3B Director's Review

Yeck, Jim jyeck at bnl.gov
Tue Aug 20 16:57:40 EDT 2024


Dear EIC Project Team:

As we approach September, it is time for us to switch gears to focus on preparation for the Director's Review on October 22-24 at BNL. Starting next week, we will begin sending calendar holds for the Dry Runs.  Page turns for each subcommittee will be self-organized by the POCs and their admins. A Kick Off meeting will be held in the next two weeks to discuss messaging, the prep site, deadlines, and templates. The prep site<https://urldefense.proofpoint.com/v2/url?u=https-3A__brookhavenlab.sharepoint.com_sites_eRHIC_Prep-5FCD-2D3B&d=DwIFAg&c=CJqEzB1piLOyyvZjb8YUQw&r=d0KG5O9luo0FhuYP-_C2VbpBNln9iudksZOBnX13nypLFx5Y3VKB85tQJ8VLc-jR&m=JjJwD4MtxBmlUDQjjfYfJasyJ8-s9z0U90q6ZEtRKZxOBOKv1z9BPavVIj3-uL-M&s=-Z4SXNjKZOGx-26WIKgF_zA-TJPrtwkyuqZs1pMsheY&e= > is live and we will be updated as more information becomes available. The PPT template on the prep site is a high-level outline. Talks should be similar to what was done for the CD-3A Review. Slides from Project Controls will be added at a later time. Cathy Lavelle will be in contact with document owners regarding needed updates.  Please review the attached Draft Agenda to see if you are a proposed speaker.

Prep Timeline:

  *   TBD-Team Prep Kickoff Meeting
  *   Sept 1-All major updates frozen in P6
  *   Sept 13 - Speakers post talk outlines to the prep site
  *   Week of Sept 16 - Page Turns
  *   Sept 19 - Supporting Document Owners send drafts to Luisella for review
  *   Sept 24 - Supporting Document Owners post final draft to the prep site
  *   Sept 26 - Speakers post draft talks to the prep site
  *   Sept 30 - October 2- Dry Runs
  *   Oct 7 - Pre-Review Meeting w/ Committee
  *   Oct 8 - Site and supporting docs are released to the review team
  *   Sept 30 - Speakers post final draft talks for QA to the prep site
  *   Week of October 14 (tentative)-Dress Rehearsals
  *   Oct 15- Presentations are posted on the review site

Review POCs and Admins:

  *   Review Coordination-Alyssa Petrone
  *   Support Coordination-Caitlin Hoffman
  *   Plenary- Luisella Lari, Admin- Mary Ellen Thelen
  *   SC1 Injectors- Sergei Nagaitsev, Admin-Dana Macciola
  *   SC2 Collider- Christoph Montag, Admin-Christina Blas
  *   SC3- Global Accelerator System- Jim Fast/Katherine Wilson, Christine Fragapane/Tammy Dellaiacono
  *   SC4 Detector- Rolf Ent/Elke Aschenauer, Admin- Anna Mendez
  *   SC5 Infrastructure- Charles Folz, Admin-Kris Schoefer
  *   SC6 Cost & Schedule- Cathy Lavelle/Kelly Krug, Admin-Donna Rassner
  *   SC7 Project Management- Luisella Lari, Admin-Mary Ellen Thelen
  *   Answers to Questions- Jim Yeck, Admin- Caitlin Hoffman

We will continue to send regular updates as plans develop.

Sincerely,
Jim
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/eicatjlab_all_personnel/attachments/20240820/2aff8e44/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: EIC CD-3B Directors Rev Agenda Draft-Rev03.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 717398 bytes
Desc: EIC CD-3B Directors Rev Agenda Draft-Rev03.xlsx
URL: <https://mailman.jlab.org/pipermail/eicatjlab_all_personnel/attachments/20240820/2aff8e44/attachment-0001.xlsx>


More information about the Eicatjlab_all_personnel mailing list