FYI, in case you have not seen the recent e-mail for coordination during the rest of the Darklight work into September.

Will

----- Forwarded Message -----
From: "Steve Benson" <felman at jlab.org>
To: dlsupport at jlab.org, "darklight" <darklight at mit.edu>
Sent: Monday, August 1, 2016 2:06:29 PM
Subject: [Dlsupport] Staffing for the upcoming installation and running of	DarkLight

Here is the current plan for staff in for the DarkLight installation and run time:


The Run Coordinator for the ongoing LERF Commissioning run is Steve Benson and the Installation Coordinator is Jim Coleman.
Jim will continue his role of Installation Coordinator in the preparation for the DarkLight run planned for 8/14 to 9/4.
Run coordinators for the DarkLight run are:

8/14-8/20:     Ross Corliss, MIT
8/21-8/27:     Jan Bernauer, MIT
8/28-9/4:       Ross Corliss, MIT

Steve Benson will be the liaison for the  LERF accelerator and Beni Zihlmann will be the liaisons for Physics.

Let me know if you have questions.

Steve Benson