Hall B is currently ramping down both the solenoid and torus magnets in support and preperation 
of the SHMS test in Hall C.

----- Original Message -----
From: "Paul Brindza" <brindza at jlab.org>
To: "esr-users" <esr-users at jlab.org>, "Cynthia Keppel" <keppel at jlab.org>, "Javier" <gomez at jlab.org>, "Howard Fenker" <hcf at jlab.org>, "Stephen Wood" <saw at jlab.org>
Sent: Monday, December 18, 2017 8:21:50 AM
Subject: [Esr-users] SHMS Dipole tests this morning

Hi


We are planning to test SHMS Dipole this morning.

Initial tests to 1300 Amps to confirm condition and operability.

This is very low impact and at 1300 Amps we are below the threshold for 
the fast dump initiated quench back and subsequent high pressure and 
high gas flow into warm return.

If these tests go OK we will request a higher current limit up to about 
2000 Amps .

This is still below the threshold for quench back.

Success means SHMS can do optics tests using the 3 pass beam.

Testing will begin about 0900 and continue to about 1200.


Cheers


Paul




_______________________________________________
Esr-users mailing list
Esr-users at jlab.org
https://mailman.jlab.org/mailman/listinfo/esr-users


More information about the Esr-users mailing list