[Esr-users] [New Logentry] Follow-up Re: Follow-up Re: Leak tests during recovery system work

kashy at jlab.org kashy at jlab.org
Mon Jul 2 17:45:02 EDT 2018


Logentry Text:
--
Chris Perry backed off the regulator PR6010 and it is now not blowing the relief valve downstream of it.
I have set up PID control to try to control between 1.3 and 1.35 atmospheres in the 3 halls.

The system needs to bleed down a bit more and I'll check back later.

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3579624