Logentry Text:
--
System modifications on the Torus and Solenoid system continued this morning.
We raised the Superconducting Helium level senosr LL8120SC by 10 inches, this should allow it to read an actual level vs 100% during stable Torus operation.
PV8674 was converted to an MV (manual valve) on Monday June 18. We need to remove the air line and update the Epics display
Also on Monday 6/18/18 RV8670 we removed the outer O-ring on the PPRV. The machined parts have come in but we are waiting for springs and thermal grease before we can put in the mechanical hardware to allow the electrical work to go forward.



---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3578576
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20180622/972d86ab/attachment.html>


More information about the Esr-users mailing list