The ESR1 to ESR2 changeover is scheduled to begin tomorrow morning, 3-5-25, at 0800. Cryo will shut off cryogens to the halls while we reconfigure the utubes from ESR1 to ESR2. We anticipate at least 4 hours before we reestablish flow. Please email me with any questions or concerns.
Brendan White
Cryogenics Electrical Engineer
Thomas Jefferson National Accelerator Facility
Jefferson Science Associates, LLC
757-269-6070 | brendanw at jlab.org<mailto:brendanw at jlab.org>
[cid:image001.png at 01DB8DC3.25345F50]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20250305/123ebf2b/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 7082 bytes
Desc: image001.png
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20250305/123ebf2b/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: ESR2 Switchover plan_v2.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 260115 bytes
Desc: ESR2 Switchover plan_v2.docx
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20250305/123ebf2b/attachment-0001.docx>
More information about the Esr-users
mailing list