The following Power Outage has been Completed:
Outage:      UIM Electrical Distribution - End Station Loop
Proposed By: Michele Solaroli
Start Time:  07/21/2014 07:00
End Time:    08/05/2014 17:00
Description/Impacts:
Work to begin on Unit Sub T9 Secondaries
For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014
Impacted Areas:
	Bldg 101: Experimental Hall A
	Bldg 102: End Station Refrigeration
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=6
    
    