[Utility Outage] Completed Power Outage - 06/30/2014 07:00
Michele Solaroli
solaroli at jlab.org
Fri Aug 15 10:04:03 EDT 2014
The following Power Outage has been Completed:
Outage: UIM Electrical Distribution - SOUTH LOOP
Proposed By: Michele Solaroli
Start Time: 06/30/2014 07:00
End Time: 08/02/2014 17:00
Description/Impacts:
South Loop power being fed from LS1, LS2 and LS3 will be shut down from 6/30/14 through 8/02/14.
For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014
Impacted Areas:
Bldg 02: South LINAC
Bldg 56: West Arc Service
Bldg 68: West Arc Service
Bldg 82: South Extractor Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=11