[Utility Outage] Scheduled Power Outage - 06/30/2014 07:00
    Michele Solaroli 
    solaroli at jlab.org
       
    Wed Jul  9 13:14:37 EDT 2014
    
    
  
The following Power Outage has been Confirmed:
Outage:      UIM Electrical Distribution - SOUTH LOOP
Proposed By: Michele Solaroli
Start Time:  06/30/2014 07:00
End Time:    07/30/2014 17:00
Description/Impacts:
South Loop power being fed from LS1, LS2 and LS3 will be shut down from 6/30/14 through 7/30/14.  LS4 and K100 will be scheduled separately when a generator arrives.  Bldg 8a - CHL Annex will be impacted.
For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014
Impacted Areas:
	Bldg 02: South LINAC
	Bldg 56: West Arc Service
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=11
    
    