[Utility Outage] Completed Power Outage - 06/25/2014 07:00

Michele Solaroli solaroli at jlab.org
Wed Jul 9 13:15:01 EDT 2014


The following Power Outage has been Completed:

Outage:      UIM Electrical Distribution - SOUTH LOOP
Proposed By: Michele Solaroli
Start Time:  06/25/2014 07:00
End Time:    07/01/2014 14:00

Description/Impacts:
Replace primary cables MVSW#7 to MVSW#3  6/25 - 6/27
Replace primary cables MVSW#3 to Unitsub FEL 6/30 - 7/1
Testing & Final Terminations 7/2 - 7/2

For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers.  Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014


Impacted Areas:
	Bldg 18: Free Electron Laser
	Bldg 36: General Purpose Building

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=8



More information about the Fac_outages mailing list